§ 4.3.19. Temporary storage of construction materials.  


Latest version.
  • Temporary storage of road construction materials, surplus material or clean fill from a county or state permitted roadway construction project may be allowed by a Temporary Use Permit issued by the Growth Services Director under the following conditions which are to be a part of the permit:

    A.

    Written permission of the property owner,

    B.

    Submittal of a sketch showing access to the storage site and location of storage area with photos attached,

    C.

    Setback of storage area shall be a minimum of 50 feet from all property lines or the setbacks of the property's zoning classification, whichever is the greatest, and

    D.

    The property shall be restored substantially to original condition within 90 days after completion of the project.

(Ord. No. 17-08, § 2(Exh. A), 4-11-2017)